Case Study · Electrical Delivery · Public Sector

Scotstoun Stadium

96 floodlights, one immovable date, and somebody else's building site.

ClientGlasgow Life
LocationScotstoun Stadium, Glasgow
EGG scopeElectrical replacement of 96 luminaire heads, four 25m masts
ProgrammePhase One summer 2025 · Phase Two early 2026
Principal contractorDYNAMIK Sport
ManufacturerAbacus

The context

A date that could not move.

In September 2024, Glasgow agreed to host the 2026 Commonwealth Games. The Opening Ceremony was set for 23 July 2026.

That left under two years to get the venues ready. Scotstoun Stadium — the Athletics venue — needed a new track, new groundworks, and floodlighting capable of meeting Commonwealth Games standard, replacing an installation whose as-installed drawings date back to 2010.

Glasgow Life appointed EGG Lighting as electrical contractor for the lighting.

The brief

Four masts. 96 heads. Two phases.

Four masts at 25 metres. 96 floodlights, 24 to a column. Two phases.

EGG's scope was the electrical work: safe isolation of each column, removal of the 96 existing heads, installation of 96 Abacus Challenger luminaires — 1500W, 5700K, DMX-driven — then testing, certification and aiming. The existing switching arrangement was retained. Abacus, as manufacturer, replaced the bracketry on the masts and carried out remedial works on the columns, with their engineers on site alongside EGG's team for much of the programme.

Work started on site on 28 July 2025 and handed over in September, in time for Glasgow Warriors' 2025/26 season and for the Athletics clubs who use the track year-round.

Phase Two, in early 2026, brought the installation up to Commonwealth Games standard.

Phasing it this way kept the stadium operating throughout. No season lost, no fixtures moved.

96

Heads replaced across four 25m masts

100%

Isolated and proved dead before work began

Two

Phases, delivered around a live venue

1,500 lux

Design level, verified on site at night

What the brief didn't say

Scotstoun in the summer of 2025 was not a lighting site. It was a track site.

Malcolm Construction had stripped out the old Athletics track and prepared the sub-base; their surfacing division, Woodholme Construction, laid the new asphalt ahead of a MONDO track installation. DYNAMIK Sport ran the site as principal contractor. EGG worked as a guest on someone else's programme — inducted by DYNAMIK, signing in and out of their logbook, agreeing access every morning.

The constraints were daily:

  • Which columns could come down was decided each morning, not in advance, depending on where the track-laying team had reached. EGG negotiated permission to lower two at a time where it would speed things up — but only with the site manager's agreement on the day.

  • A lowered column lies across the track. Where new surface was already down, 18mm plywood protection went down first.

  • The telehandler needed for the bracket work couldn't go on a wet track — in Glasgow, in August — and couldn't be left on the track overnight under any circumstances.

  • Part of the on-site storage building was unusable due to RAAC in the rear rooms, restricting materials handling to the front section only.

None of it was negotiable. None of it moved the Games.

How it was delivered

Not heroics. Procedure, and a conversation every morning.

Every column was isolated before anyone touched it

Point of isolation identified, locked off, labelled, key retained by the operative doing the work. Proved dead across every combination of line, neutral and earth, with the test equipment itself proved before and after. No live working was permitted on this project under any circumstances, and the risk assessment said so in terms. All electricians on site worked to 18th Edition, with an SSSTS operative present at all times.

The cabling was specified on site, not at order stage

The runs between luminaire and driver could only be settled once the masts were surveyed — lengths and terminations aren't knowable when an order is placed. EGG specified it: 8-core H07RN-F 8×1.0mm². A small thing that becomes a large thing if you find it in week three with a track going down around you.

The drivers sit at the base of each column, not at the head

The column had a weight limit, so low-level mounting was the sound structural choice. It also means a driver failure can be attended from ground level — without lowering a mast or booking a lift. The drivers are DMX compatible, so the installation is not locked to one luminaire for its service life.

The sequence was built to be reordered, not queued

If the track team's progress ruled out a column that morning, the crew moved to another rather than standing down. Heads were installed per the lighting design documentation, mast section by mast section, pre-aimed from ground level as closely as design allowed, with an IPAF operative and a lift later in the programme for final aiming.

The day ended the same way every day

Circuits made safe and re-energised where safe to do so. Plant stored clear of the track works. A daily handover to the DYNAMIK site manager setting out the next day's working area, and a daily report back to EGG head office.

Testing followed the full sequence — continuity, insulation resistance, polarity, earth fault loop impedance, prospective fault current, RCD and phase sequence — with Minor Works Certificates and lux readings required at handover. The 96 removed heads, redundant cabling and packaging were returned to EGG's stores for recycling.

Verified on site

The design document specified 1,500 lux across the field of play, with a tolerance of 10%. The team walked the arena at night, taking readings against the design figures. Every reading fell inside the tolerance.

EGG engineer on a MEWP alongside a Scotstoun floodlight mast head frame
Scotstoun Stadium track and floodlight masts in daylight
Scotstoun floodlight mast lit under a double rainbow

The result

Six days, in front of the world.

Glasgow 2026 ran for 11 days. For six of them — 27 July to 1 August — Scotstoun hosted the Athletics and Para Athletics programmes: 43 and 16 medal events across 12 sessions.

The lighting performed throughout.

Scotstoun Stadium full of spectators during Glasgow 2026 Athletics
Medal ceremony at Scotstoun under the floodlights during Glasgow 2026
Evening Athletics session at Scotstoun under floodlight during Glasgow 2026

The company we keep

A competition surface, and lighting measured against its own specification.

The track EGG worked around is a MONDO installation, specified to a competition standard. The lighting was specified to 1,500 lux across the field of play and verified against it on site. A venue needs both to keep hosting championships.

It was never a temporary build. After Glasgow 2026 the MONDO surface stays, Glasgow Life continues to operate the venue, and scottishathletics gains another competition track.

Lighting is part of that legacy. The floodlighting EGG installed is what lets the venue keep hosting championships long after the Games have moved on.

  • The surface remains

    MONDO track stays in place post-Games

  • Operated locally

    Glasgow Life runs the venue year-round

  • Community use

    Athletics clubs train on it week in, week out

  • Future championships

    A venue that can host at the top level

There is no version of this project where the lighting is finished late, or finished badly and fixed afterwards. The track goes down, the venue hands over, the world arrives.

For work where the consequence of getting it wrong is public and permanent, the measure of a contractor is whether anyone had to think about them at all.

Not our first visit to Scotstoun

The stadium is the most visible part of a longer relationship.

EGG has worked across the wider Scotstoun campus for Glasgow Life since 2023.

YearProjectScope
2024Scotstoun 11sNew LED floodlighting across six columns, fully certificated
2025–26Scotstoun Stadium96-head replacement, brought up to Commonwealth Games standard

By the time the stadium work started, EGG was not a new contractor learning a venue. It was the team that already knew it.

Electrical delivery for venues that can't close.

Full electrical contracting capability, on programmes that cannot slip, alongside contractors we do not control.

Conversation, not tender

Start with a conversation.

No tender process required. No sales pressure. A straight answer about what your estate is worth.